Campus Construction Updates
Projects/Dates Impact

439 College Street Renovation
December 17, 2018 - July 19, 2019

ReArch Company will be renovating 439 College Street.  The building and parking lot will be unavailable for use and under construction from December 17, 2018 until July 19, 2019.  The site will be fenced per the attached site plan.  

Some localized construction noise and activity impacts will occur.

Aiken Makerspace - Eco-Machine Removal
June 10 - August 16, 2019
Contractor will be removing the Eco-Machine, replacing concrete floor, add drainage, installation of grow lights and minor wall relocation for access to the space.  All construction activity will occur via the loading dock and the dumpster will be located in the loading dock area. 

Some localized construction noise will occur.

Morrill Suite 004 and Classroom 005
June 17 – August 30, 2019
Work will include new finishes, HVAC and electrical.  Some localized construction noise and activity impacts will occur.
On Campus Multipurpose Center
May 22, 2019 – June 30, 2021

The Patrick/Forbush/Gutterson Complex will receive an upgrade and expansion to UVM’s athletic facilities. 

The road between PFG Road and Davis Road and the Horseshoe parking lot will be closed to vehicle and pedestrian traffic.  The south exit on the upper level of the parking garage will be closed but north access will remain open.  All horseshoe parking lot access doors, loading dock, upper stairs to PFG will be closed.  Field 5 on the south side of PFG will become a contractor staging area and a construction access route will be installed along the west side of PFG

 

Stafford Interior Renovations
June 2019 – January 2020
Architectural and aesthetic upgrades as well as tel/data mechanical, lighting and electrical, and controls upgrades to Level Two will happen in two phases starting in the summer of 2019 and completing early 2020. Additional lighting and electrical, and tel/data work will happen at Levels Three and Four. Minor facilitating work will occur on all floors.

During construction, the main corridors will be open and usable for egress from the building.  Some localized construction noise and activity impacts will occur and these will be managed as best they can by the contractor.

UVM Ropes Course
June 13 – July 15, 2019
Work will include installation of a gravel support pad and a new shed. There will be minimal vehicular traffic impact near the South Burlington Rec. Path.
Waterman Office Suite 354, 355 & 357
June 17 - 28, 2019
Work will include new paint and replacement of carpeting.

 

Quick Links