2026 Shutdown Schedule
The buildings listed below will be impacted by the annual maintenance shutdown. Click on your building name to expand the schedule details. If your building is not listed, then it will not be impacted.
Why do we conduct an annual shutdown?
Each spring, the Physical Plant department performs an annual shutdown of the Main Campus District Energy Plant and satellite boilers to complete mandatory equipment and safety inspections and to perform critical maintenance repairs on the campus thermal energy distribution system.
The shutdown impacts the heating, cooling and hot water system in many campus buildings. The process typically begins immediately after the main Commencement Ceremony has ended and continues for several days. The detailed schedule of impacts is published a few weeks prior to shutdown.
We appreciate the patience and cooperation of campus partners and building occupants during this brief disruption. Please direct all questions or concerns to Service Operations Support (SOS) and they will route you to the appropriate field maintenance or engineering personnel.
Email: sos@uvm.edu
Phone: 802-656-2560
Given Boilers
Given Complex, Converse Hall
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) goes offline at 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| Given Boiler Plant will be in operation to provide heating, hot water and critical air conditioning. No Cage Washing. No Autoclaves. | Given Boiler Plant will be in operation to provide heating, hot water and critical air conditioning. No Cage Washing. No Autoclaves. | Given Boiler Plant will be in operation to provide heating, hot water and critical air conditioning. No Cage Washing. No Autoclaves. | Given Boiler Plant will be in operation to provide heating, hot water and critical air conditioning. No Cage Washing. No Autoclaves. | Given Boiler Plant will be in operation to provide heating, hot water and critical air conditioning. No Cage Washing. No Autoclaves. | Given Boiler Plant will be in operation to provide heating, hot water and critical air conditioning. No Cage Washing. No Autoclaves. |
Rowell Hall and Health Science Research Facility (HSRF)
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant Steam (CUP) goes offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution goes online at 3:00 PM |
| No Cage Washing. No Autoclaves. Rowell, HSRF will have limited air conditioning from CUP | No Cage Washing. No Autoclaves. Rowell, HSRF will have limited air conditioning from CUP | No Cage Washing. No Autoclaves. Rowell, HSRF will have limited air conditioning from CUP | No Cage Washing. No Autoclaves. Rowell, HSRF will have limited air conditioning from CUP | No Cage Washing. No Autoclaves. Rowell, HSRF will have limited air conditioning from CUP | No Cage Washing. No Autoclaves. Rowell, HSRF will have limited air conditioning from CUP |
MLS Boilers
Marsh Life Science (MLS), Carrigan Wing, Aiken Building, Stafford Greenhouse
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| MLS Boiler Plant will be in operation to provide limited heating and hot water. MLS, Carrigan, Aiken will have limited air conditioning from CUP. | MLS Boiler Plant will be in operation to provide limited heating and hot water. MLS, Carrigan, Aiken will have limited air conditioning from CUP. | MLS Boiler Plant will be in operation to provide limited heating and hot water. MLS, Carrigan, Aiken will have limited air conditioning from CUP. | MLS Boiler Plant will be in operation to provide limited heating and hot water. MLS, Carrigan, Aiken will have limited air conditioning from CUP. | MLS Boiler Plant will be in operation to provide limited heating and hot water. MLS, Carrigan, Aiken will have limited air conditioning from CUP. | MLS Boiler Plant will be in operation to provide limited heating and hot water. MLS, Carrigan, Aiken will have limited air conditioning from CUP. |
Stafford Hall
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| No Steam. No Heat. No hot water. No Cage Washing. No Autoclaves. Stafford will have limited air conditioning from electric chillers. | No Steam. No Heat. No hot water. No Cage Washing. No Autoclaves. Stafford will have limited air conditioning from electric chillers. | No Steam. No Heat. No hot water. No Cage Washing. No Autoclaves. Stafford will have limited air conditioning from electric chillers. | No Steam. No Heat. No hot water. No Cage Washing. No Autoclaves. Stafford will have limited air conditioning from electric chillers. | No Steam. No Heat. No hot water. No Cage Washing. No Autoclaves. Stafford will have limited air conditioning from electric chillers. | No Steam. No Heat. No hot water. No Cage Washing. No Autoclaves. Stafford will have limited air conditioning from electric chillers. |
Leahy Building, Howe Library, CCRH (Central Campus Residence Hall)
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| No Steam. No Heat. No hot water. No Autoclaves. Howe and CCRH will have limited air conditioning from CUP. | No Steam. No Heat. No hot water. No Autoclaves. Howe and CCRH will have limited air conditioning from CUP. | No Steam. No Heat. No hot water. No Autoclaves. Howe and CCRH will have limited air conditioning from CUP. | No Steam. No Heat. No hot water. No Autoclaves. Howe and CCRH will have limited air conditioning from CUP. | No Steam. No Heat. No hot water. No Autoclaves. Howe and CCRH will have limited air conditioning from CUP. | No Steam. No Heat. No hot water. No Autoclaves. Howe and CCRH will have limited air conditioning from CUP. |
Central Campus
Billings, Billings Addition, Williams Hall, Old Mill/Lafayette, Royall Tyler, Davis Center, Terrill, Jeffords, Discovery Hall & Innovation Hall, Firestone Medical Research Building
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| No Steam. No Heat. Limited or no hot water. No Autoclaves. Firestone will have heating hot water fed from HSRF. These buildings (except Williams) will have limited air conditioning from CUP. | No Steam. No Heat. Limited or no hot water. No Autoclaves. Firestone will have heating hot water fed from HSRF. These buildings (except Williams) will have limited air conditioning from CUP. | No Steam. No Heat. Limited or no hot water. No Autoclaves. Firestone will have heating hot water fed from HSRF. These buildings (except Williams) will have limited air conditioning from CUP. | No Steam. No Heat. Limited or no hot water. No Autoclaves. Firestone will have heating hot water fed from HSRF. These buildings (except Williams) will have limited air conditioning from CUP. | No Steam. No Heat. Limited or no hot water. No Autoclaves. Firestone will have heating hot water fed from HSRF. These buildings (except Williams) will have limited air conditioning from CUP. | No Steam. No Heat. Limited or no hot water. No Autoclaves. Firestone will have heating hot water fed from HSRF. These buildings (except Williams) will have limited air conditioning from CUP. |
Votey Boilers
Votey, Kalkin/Ifshin Building, Perkins Hall, Fleming Museum,
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| Votey Boiler Plant will be in operation to provide limited heating and hot water. Votey and Kalkin will have limited air conditioning. Fleming and Perkins air conditioning will not be impacted. | Votey Boiler Plant will be in operation to provide limited heating and hot water. Votey and Kalkin will have limited air conditioning. Fleming and Perkins air conditioning will not be impacted. | Votey Boiler Plant will be in operation to provide limited heating and hot water. Votey and Kalkin will have limited air conditioning. Fleming and Perkins air conditioning will not be impacted. | Votey Boiler Plant will be in operation to provide limited heating and hot water. Votey and Kalkin will have limited air conditioning. Fleming and Perkins air conditioning will not be impacted. | Votey Boiler Plant will be in operation to provide limited heating and hot water. Votey and Kalkin will have limited air conditioning. Fleming and Perkins air conditioning will not be impacted. | Votey Boiler Plant will be in operation to provide limited heating and hot water. Votey and Kalkin will have limited air conditioning. Fleming and Perkins air conditioning will not be impacted. |
Torrey Hall, Ira Allen Chapel/CC Theatre
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| No Steam. No Heat. Limited or no hot water. Ira Allen/CC Theatre will have limited air conditioning. | No Steam. No Heat. Limited or no hot water. Ira Allen/CC Theatre will have limited air conditioning. | No Steam. No Heat. Limited or no hot water. Ira Allen/CC Theatre will have limited air conditioning. | No Steam. No Heat. Limited or no hot water. Ira Allen/CC Theatre will have limited air conditioning. | No Steam. No Heat. Limited or no hot water. Ira Allen/CC Theatre will have limited air conditioning. | No Steam. No Heat. Limited or no hot water. Ira Allen/CC Theatre will have limited air conditioning. |
South Campus
University Heights North, University Heights South
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| No Steam. No Heat. No hot water. No air conditioning. | No Steam. No Heat. No hot water. No air conditioning. | No Steam. No Heat. No hot water. No air conditioning. | No Steam. No Heat. No hot water. No air conditioning. | No Steam. No Heat. No hot water. No air conditioning. | No Steam. No Heat. No hot water. No air conditioning. |
South Campus Boilers
Mason, Simpson, Hamilton (MSH), Coolidge, Redstone Hall, Music Building, Southwick, Christie, Wright, Patterson (CWP), Robinson, Slade Hall, Wing Davis Wilks (WDW), Living & Learning (L&L)
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| Satellite Boiler Heating Plants will be in operation to provide heating, hot water, and steam. Additional facility shutdowns will be completed throughout the summer if not completed during shutdown week. | Satellite Boiler Heating Plants will be in operation to provide heating, hot water, and steam. Additional facility shutdowns will be completed throughout the summer if not completed during shutdown week. | Satellite Boiler Heating Plants will be in operation to provide heating, hot water, and steam. Additional facility shutdowns will be completed throughout the summer if not completed during shutdown week. | Satellite Boiler Heating Plants will be in operation to provide heating, hot water, and steam. Additional facility shutdowns will be completed throughout the summer if not completed during shutdown week. | Satellite Boiler Heating Plants will be in operation to provide heating, hot water, and steam. Additional facility shutdowns will be completed throughout the summer if not completed during shutdown week. | Satellite Boiler Heating Plants will be in operation to provide heating, hot water, and steam. Additional facility shutdowns will be completed throughout the summer if not completed during shutdown week. |
Marsh, Austin, Tupper (MAT), Harris/Millis
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 6:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| MAT Boiler Heating Plant will be in operation to provide heating, hot water and steam. | MAT Boiler Heating Plant will be in operation to provide heating, hot water and steam. | No Heat. No Hot Water. MAT Boiler Plant will be off line. | MAT Boiler Heating Plant will be in operation to provide heating, hot water and steam. | MAT Boiler Heating Plant will be in operation to provide heating, hot water and steam. | MAT Boiler Heating Plant will be in operation to provide heating, hot water and steam. |
PFG Gym Complex
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 Central Utility Plant (CUP) offline 1:00 PM | Day 1 CUP off-line all day | Day 2 CUP off-line all day | Day 3 CUP off-line all day | Day 4 CUP off-line all day | Day 5 Steam distribution online at 3:00 PM |
| The PFG Boiler Plant will be in operation to provide heating, hot water and steam | The PFG Boiler Plant will be in operation to provide heating, hot water and steam | The PFG Boiler Plant will be in operation to provide heating, hot water and steam. | The PFG Boiler Plant will be in operation to provide heating, hot water and steam | The PFG Boiler Plant will be in operation to provide heating, hot water and steam | The PFG Boiler Plant will be in operation to provide heating, hot water and steam |
Waterman Boilers
Waterman Building
| Sunday 17 May 2026 | Monday 18 May 2026 | Tuesday 19 May 2026 | Wednesday 20 May 2026 | Thursday 21 May 2026 | Friday 22 May 2026 |
|---|---|---|---|---|---|
| Day 0 | Day 1 | Day 2 | Day 3 | Day 4 | Day 5 |
| All systems online, and operating as normal. | All systems online, and operating as normal. | All systems online, and operating as normal. | All systems online, and operating as normal. | All systems online, and operating as normal. | All systems online, and operating as normal. |
We appreciate the patience and cooperation of campus partners and building occupants during this brief disruption.
Please direct all questions or concerns to Service Operations Support (SOS) and they will route you to the appropriate field maintenance or engineering personnel.
Email: sos@uvm.edu
Phone: 802-656-2560