Prior to the commencement of any environmental remediation activity on campus such as asbestos abatement or lead paint removal. The Environmental Health and Safety office will notify occupants of the areas which may be impacted or disrupted by the project activities.
Asbestos Abatement Notices
Rowell Hall Rooms 103, 108, 109
Body
WHAT IS HAPPENING?
As part of renovations, Environmental Hazards Management, Inc. will remove 80 SQFT of Chalk Boards and Associated Adhesive in room 103.
Rooms 108 & 109 removal of 680 SQFT of Flooring and Mastic/Adhesive and 50 Linear Feet of Caulking.
DURATION OF WORK:
Start Date: Monday, May 12, 2025
Completion Date: Friday, May 16, 2025
Hours: 6-4:30