Duration of Work:
Revised schedule
Start of Work: 12/15/2025
Completion Date: 12/23/2025
No Work on 12/24/2025 thru 01/04/2026
Start of Work: 01/05/2026
Completion Date: 01/16/2026
What Is Happening?
Steam and condensate piping work in the Terrill Building.
What to Expect:
Cooper Mechanical will be working in the Terrill Building steam tunnel. Fans will be used to remove welding smoke and odors from the work area. Expect localized construction noise and smells during this work. The contractor will manage the noise and odors to the greatest extent possible. See access areas below and fan locations below. Locations are subject to change based on project conditions.
Printable Project Notice (PDF)
Construction Questions:
Kevin Sweeney, Project Coordinator
Facilities Management/Utilities Engineering
Phone: 802-656-2623
Email: Kevin.Sweeney@uvm.edu