Duration of Work: 

Start of Work: 1/5/2026

Completion Date:  4/21/2026
 

What Is Happening?

The project at the UVM Colchester Research Facility involves a comprehensive electrical service upgrade, including the installation of new underground primary and secondary electrical conduits, new vaults, and a new 1000 kW diesel generator on a concrete pad 
 

What to Expect:

Some localized construction noise and activity impacts will occur, and the contractor will manage them as best they can.

Areas and Buildings Affected:

  • Colchester Research Facility
  • Rooms 133, 134 and 140
  • Limited impact to the East side of Lab 130. 
     

Construction Questions:

UVM Planning, Design and Construction, 802-656-3291

Project Manager:
Scott Miller
Phone: 802-922-7973
Email: slmiller@uvm.edu