YEAR-END OPERATIONAL SCHEDULE: JUNE 30, 2005
               
DATE DAY JOB # ASSIGNED OLD YEAR TASK (FY05) -- FY2005 JOB # ASSIGNED NEW YEAR TASK (FY06) -- Fiscal Year 2006
03/29 Tuesday      
03/30 Wednesday            
03/31 Thursday            
04/01 Friday     MARCH MONTH-END      
04/04 Monday            
04/05 Tuesday       ZEKE wvw / smr / lad Set up FRS and HRS calendars in ZEKE: ACME, APPUME, ACQTR, FRSCLOSE,FRSCLOSE1,FRSCLOSE2,FRSCLOSE3 ,NYDISPLY, EJMONTH,EJCOMB,EJQRT,EJSAL,EJWEEK. Update ZEKE events that require specific dates - See FRSFYEZ.DOC.
04/06 Wednesday            
04/07 Thursday            
04/08 Friday PLUSACW ZEKE Weekly FRS job stream      
04/11 Monday   wvw Change HRS June Month-End in Zeke to date of FRS 1st Close - 7/1/05.    
04/12 Tuesday            
04/13 Wednesday            
04/14 Thursday            
04/15 Friday PLUSACW ZEKE Weekly FRS job stream      
04/18 Monday            
04/19 Tuesday            
04/20 Wednesday            
04/21 Thursday            
04/22 Friday            
04/22 Friday PLUSACW ZEKE Weekly FRS Job Stream      
04/25 Monday            
04/26 Tuesday            
04/27 Wednesday            
04/28 Thursday FJMOFBCA ZEKE / lad Monthly FB-update.      
04/29 Friday FJY674JA ZEKE / mml SGA Open Commitments Report.      
04/29 Friday   lad Update REPORT DESCRIPTION FILE - Message on FBM090      
04/29 Friday     APRIL MONTH-END      
05/02 Monday FJY506EA FJY514EA ZEKE/ mml / msw Compare yr-end and delete flags - SL/GL -- these jobs spool to FRSL.      
05/03 Tuesday   lys 1st memo on closing. Put on Catskill, ACED, and ZERO18000S.      
05/04 Wednesday            
05/05 Thursday            
05/06 Friday PLUSACW ZEKE Weekly FRS job stream      
05/06 Friday   GCA New Year Agriculture Accounts MUST BE CREATED PRIOR TO THIS DATE    
05/09 Monday            
05/10 Tuesday            
05/11 Wednesday   lad / smr Review all daily, weekly, monthly, quarterly, and yearly jobs, for dates that need to be changed. These must be completed by 5/27/05.    
05/12 Thursday            
05/13 Friday PLUSACW ZEKE Weekly FRS Job Stream      
05/13 Friday PLUSCHARTS ZEKE Chart of Accounts & Attribute Listings      
05/16 Monday            
05/17 Tuesday            
05/18 Wednesday            
05/19 Thursday            
05/20 Friday PLUSACW ZEKE Weekly FRS job stream.      
05/23 Monday            
05/24 Tuesday            
05/25 Wednesday            
05/26 Thursday YREND02B EZT lys Review for IDP Income + Reverse.      
05/26 Thursday FJMOFBCA ZEKE / lad Monthly FB-update.      
05/27 Friday FJY554JA ZEKE / mml Run Capitalization Report (Should run at May Month End Time)   FAB Bullseye user budgets due.
05/27 Friday FJY674JA ZEKE / mml SGA Open Commitments Report.      
05/27 Friday   lad Update REPORT DESCRIPTION FILE - Message on FBM090      
05/27 Friday   ZEKE May Monthly reports begin.      
05/27 Friday HJFOCSCA ZEKE / wvw / mjk / mm HRS Monthly Focus Reports. Output should go to Mike Meunier.      
05/27 Friday PLUSAPM PLUSPUM PLUSACM ZEKE Accts. Payable Month End, Purchasing Month End, Month-End Mechanical Entries.    
05/27 Friday PLUSQTR ZEKE Run QUARTERLY REPORTS - FY05 ONLY.      
05/27 Friday FJM534EA FJM538EA FJM540EA lat / dh / slb Verification of open commitments begins: Ledgers 2-xxxxx and 3-xxxxx, 6-28xxx thru 9-xxxxx, Travel and Work Orders. Physical Plant verifies contracts. Work Control checks work order commitments.  
05/27 Friday   smr / lad Make sure FRSREPS cms account reads all files in for Saturday morning. Also ensure the CMS AND WEB budget reports are available, and look good.  
05/27 Friday PLUSAYE ZEKE Annual EZTrieves run and verified.      
05/27 Friday MAY MONTH-END
05/30 Monday MEMORIAL DAY HOLIDAY
05/31 Tuesday         smr / CIT Set up tape datasets for new fiscal year: FRD906MV, FRT906MB, FRT906MI, FRT906MV, FRVVH06A, FRVVH06I, FRYTD06A, FRYTD06I. Must be done before 1st close.
05/31 Tuesday   mml Identify projects for capitalization entries. EJA520BA / EJM570BA ZEKE / wvw Position control list with encumbrance feed to acctng. suppressed. These jobs should be run weekly until 7/01/05. FY06 only.
05/31 Tuesday   lys 2nd memo on closing. Put on Catskill, ACED, ZERO18000S and Controller's Lists.  
05/31 Tuesday YREND02A EZT lys Subagency Report for CE to review.      
05/31 Tuesday   jsk Memo to people doing on-line banner entries. Re: Notification to JSK of old year billings done after 6/30.  
05/31 Tuesday   ALL Lois Schuster approves all interfund transfers from this point forward until final closing.    
05/31 Tuesday FJY506EA FJY514EA ZEKE / mml / msw Compare yr-end and delete flags - SL/GL -- these jobs spool to FRSL.      
06/01 Wednesday            
06/02 Thursday   ALL LAST DAY TO DELETE OLD YEAR ACCOUNTS. After today, do not process any account deletes to the old or new year until final closing has been completed.  
06/02 Thursday   FAB Load necessary accounts for use when loading new year budgets      
06/03 Friday   ALL Final account creates before FY06 skeleton master file is created. Starting 6/06/05, *** YOU MUST CREATE IN BOTH YEARS ----- ON THE SAME DAY. *** EJA520BA / EJM570BA ZEKE / wvw Position control list with encumbrance feed to acctng. suppressed. These jobs should be run weekly until 7/01/05. FY06 only.
06/03 Friday PLUSACW ZEKE Weekly FRS Job Stream.   smr / lad CREATE ORACLE TABLES FOR THE NEW YEAR. ** Look for additional HRS Tables that aren't in Lad's notes!!! **
06/03 Friday   ALL Final attribute changes before FY06 skeleton master file is created.Starting 6/06/05, YOU MUST CHANGE ATTRIBUTE IN BOTH YEARS. WAGE / SAL Run percentage increase report.
06/03 Friday     FJD043AA FJD043AB FJD043AC smr / lad Needs to be run both old and new year from 6/3 -9/26.
06/03 Friday       PLUSFRY1 smr / lad Skeleton Master File create (GL, SL, OC, Suspense, Batch Files) YEAR END JOBS TO BE RUN - FJY001, FJY007 & FJY006. SMR -- Make sure FJY001JA runs okay, and new year files are created over the weekend.** IMPORTANT ---- SMR ---- PLEASE MAKE SURE THAT THESE JOBS DON'T RUN OUT OF DISK SPACE.
06/03 Friday   smr Verify Skeleton Files. PLUSNYCC smr / lad Attribute list (FBM042) & Chart of Accounts (FBM040) run. NOTE: Part of daily after FBY001
**** FROM THIS POINT FORWARD, ALL BATCH HEADERS MUST INDICATE FY05 (2005) OR FY06 (2006)! BE CAREFUL! ****            
               
06/06 Monday   ALL Reminder: DO NOT PROCESS ANY ACCOUNT DELETES TO THE OLD OR NEW YEAR UNTIL AFTER FINAL CLOSING IS COMPLETED -- (approx. 9/27/05 --- this date is subject to change). ALL Reminder: DO NOT PROCESS ANY ACCOUNT DELETES TO THE OLD OR NEW YEAR UNTIL AFTER FINAL CLOSING IS COMPLETED -- (approx. 9/27/05 -- this date is subject to change).
06/06 Monday   ALL ANY REQUESTS FOR HAND-DRAWS MUST BE APPROVED BY MOLLY LOWDER OR LOIS SCHUSTER FROM THIS POINT FORWARD. AIS Display file chart (FBM040) created (D NEWCHART). AVAILABLE 6/06/05.
06/06 Monday       FJM040JA FJM009J1 FJM061J1 Zeke / lad These are new year display files that run from 6/06/05-7/22/05. They are scheduled using the calendar NYDISPLY. They do not get scheduled after the 3rd run.
06/06 Monday         PUR Start printing New Year orders.
06/06 Monday       FJY506EB FJY514EB ZEKE / mml / msw Compare year-end flags & delete flags - SL/GL ---- these jobs spool to FRSL.
06/06 Monday         smr CREATE AND SCHEDULE FRS TO ORACLE CONVERSION JOBS.
06/06 Monday         cll ADD NEW YEAR TABLES TO PL / SQL PACKAGES.
06/07 Tuesday   FINA / SFS Award Payment Program and Microfaid Awards Run. (FINAL MED LOANS awarded LAST JUNE DATE.)  
06/08 Wednesday TELEPHONE CHARGES bjh / lad Create PBX charges: RUN TELEPHONE CHARGE TRANSACTIONS AND FTP TO GIRAFFE FOR UPDATING.    
06/08 Wednesday   GCA Verify Financial Aid accounts for Flags.      
06/09 Thursday TC6670EA and TC6670EB ONLY lad June PBX distributed as final liquidation of commitment (Approx). No old encumbrances to be created.  
06/09 Thursday   FINA / SFS Award Payment Program run.      
06/10 Friday TC6680JA lad DO NOT RUN TC6680EA AT THIS TIME!!!!! CHANGE YEAR IN JCL AND DATE TO 6/30/05 - DON'T LOAD UNTIL 7/18 NEW YEAR AND NOT UNTIL GENERAL FUND BUDGETS ARE LOADED FROM FAB. LOAD WITH TCE DISK (60 day retention on TCE disk, per smr). **** MAKE SURE CALCULATIONS ARE ACCURATE (especially with grants)!!  
06/10 Friday PLUSACW ZEKE Weekly FRS Job Stream. EJA520BA / EJM570BA ZEKE / wvw Position control list with encumbrance feed to acctng. suppressed. These jobs should be run weekly until 7/01/05. FY06 only.
06/10 Friday   mml Verify Cochran lease purchase payment for imputed interest      
06/13 Monday FJM111EA DATA ljd / lad Endowment Income distribution.  
06/13 Monday FJM111EB ljd / lad Endowment Income distribution to FRS.      
06/13 Monday   mml / lrs Copy of EPV's > $1000 Not Paid By Last Old Year P/R to MML for Salary/Fringe Accrual.  
06/14 Tuesday   FINA / SFS Financial Aid Payments and Microfaid Awards Run -FY05 (NO LOANS)      
06/15 Wednesday   PUR DEADLINE for 05 Requisitions for Purchase Orders for GENERAL FUNDS ONLY.    
06/16 Thursday   FINA / SFS FINAL award payments for old year run. ALL FINANCIAL AID PROGRAMS HEREAFTER ARE NEW YEAR.  
06/17 Friday PLUSCHARTS ZEKE Chart of Accounts & Attribute Listings.      
06/17 Friday PLUSACW ZEKE Weekly FRS job stream. EJA520BA / EJM570BA ZEKE / wvw Position control list with encumbrance feed to acctng. suppressed. These jobs should be run weekly until 7/01/05. FY06 only.
06/20 Monday            
06/21 Tuesday            
06/22 Wednesday            
06/23 Thursday            
06/24 Friday         GCA Make sure Financial Aid accounts are thawed for July 1 updates.
06/24 Friday       EJA520BA / EJM570BA ZEKE / wvw Position control list with encumbrance feed to acctng. suppressed. These jobs should be run weekly until 7/01/05. FY06 only.
06/27 Monday   AUX Central Stores closed Monday, June 27th through Thursday, June 30th, for billing and physical inventories. AP must get all invoices to Central Stores ASAP.    
06/27 Monday   CENTRAL STORES DEADLINE: Central Stores FY05 orders must be processed.      
06/27 Monday   AUX Telcom Supplies Inventory 6/27 - 7/1/05. Telcom office remains open.      
06/27 Monday   AUX Microcomputer Depot Inventory 6/27 - 7/1/05. Depot remains open.      
06/27 Monday   AUX Fleming Museum Gift Shop inventory.      
06/28 Tuesday   ALL LAST University Store purchases in FY05.      
06/28 Tuesday   ZEKE / lrs Semi-monthly payroll dated 6/28 (for June 30th) run and updated into FRS. *** THIS IS THE LAST FRS OLD YEAR (FY05) PAYROLL!!  
06/28 Tuesday   pas / krs Verify date of bank withdrawal for Payroll taxes and process DCA to appropriate fiscal year.  
06/29 Wednesday EJA490BB mpp / gab / js This job should run against the old year (after the last FRS old year payroll), in order to CALCULATE retroactive payroll transactions, but this job does not update them. At this point in time, these entries have to be manually written up, ** see the line below.** This job should run daily from 6/29/05 through 2nd run (7/15/05).  
06/29 Wednesday   mpp / gab / js / GCA Retroactive payroll entries after 6/28 payroll is run, require journal entries to also include manual fringe distribution. GACA APPROVES Payroll Records input.  
06/29 Wednesday   AUX University Store closed June 29th through June 30th for Physical Inventory.    
06/29 Wednesday FJY502JA ZEKE / lys Verify gift attributes. Spool to COMPMML.      
06/29 Wednesday FJCOMPJA / EVENT 161 ZEKE / ljd Check OLD GL against NEW GL , OLD SL against NEW SL. View on FRSL.  
06/30 Thursday   CASH Cashier's Office requests cash by 12:00 noon. Gifts to Gift Records by 9:00 a.m. - Specify FY05.  
06/30 Thursday   CASH Cashier's Office open 8:00 a.m. - 4:00 p.m.      
06/30 Thursday   CASH Cashier continues to process Old Year Batches for cash deposited to banks before 7/1.    
06/30 Thursday   A/R / SFS DEADLINE: A/R on-line billing input for 6/30 ageing      
06/30 Thursday   A/R / SFS Final FRS update for ageing. Run special 6/30 ageing for comparison      
06/30 Thursday   A/P UNIVERSITY STORE FINAL Store purchase journal after POCs cashed in June are updated. If any entries done after this date, this will need to be run again. GCA, A/P & FAB Mechanical entries examined for FY06, revisions to be processed by 7/22.
06/30 Thursday   ALL Last Print & Mail Center processed orders for FY05.      
06/30 Thursday   AUX / mml ALL INVENTORY ADJUSTMENTS SHOULD BE BROUGHT TO Molly Lowder in the General Accounting Office BY 7/14/05. NEEDS TO BE BOOKED BY SECOND RUN.  
06/30 Thursday   AUX Biology stockroom Inventory - 6/30/05 closed all day, will reopen on 7/1/05.    
06/30 Thursday   AUX Environmental Safety Facility -- Chemsource Inventory.      
06/30 Thursday   bc Coordinates year-end confirmation letters      
06/30 Thursday   G/A From this point forward all old year hand-drawn checks require a DCA to set up payable. When processing new year hand-draws, verify year to which you are processing.  
06/30 Thursday YREND02B EZT lys Review for IDP Income + Reverse.      
06/30 Thursday   Zeke / smr / lad Run 2 jobs for Linda Schneider, FJM061B1 (648), and FJM095BA (594).    
06/30 Thursday FJMOFBCA ZEKE / lad Monthly FB-update.      
07/01 Friday LAST ENTRIES ON FIRST RUN
07/01 Friday HJFOCSCA ZEKE / wvw / mjk / mm HRS Monthly Focus Reports. Output should go to Mike Meunier. EJA520BA / EJM570BA ZEKE / wvw Position control list with encumbrance feed to acctng. suppressed. These jobs should be run weekly until 7/01/05. FY06 only.
07/01 Friday   ALL / A/P NO NEW YEAR EXPENSES ON PREPAID ACCOUNTS, ALL TRANSACTIONS SHOULD BE CHARGED TO NEW YEAR BUDGETS. jsk / lad / smr $BANFY = 06 (Zeke variable change) Set to new year July 1st (Jill to call Laurie Desso, and send e-mail to Laurie and Steve Rose, Laurie will change Zeke variable.
07/01 Friday FJM532AB ZEKE / mm Run Daily until the end of closing (3RD RUN). OC report/matrix   PUR Purchasing will begin to issue P.O.C. charged to New Year (FY06) budgets.