Project Timeline

Timelines will be progressively elaborated as details are determined. All dates are subject to change.

FSCM/ Financials System 9.2 Upgrade

Time Period Phase
Fall 2015 to Fall 2017 Planning and Research
Fall 2017 Technical work begins
Jan - March 2018 Functional testing
April 5, 2018 Go-live decision
April 5, 2018 Last day to submit expense reports
Last day to enter/submit requisitions
April 9, 2018 Last day for departmental approval of expense reports
April 12 - 15, 2018 System closed to users at 5pm on April 12 for upgrade work
April 16, 2018 System reopens to all users for all functionality