Pomeroy Hall Ductwork Cleaning

August 1 – August 19, 2016

DESCRIPTION OF WORK

Duct Cleaning Contractor (VENTTEC / Russell Payne) will be on-site in Pomeroy Hall starting, early in the morning, August 1, 2016.  The estimated project completion should be the end of the day, August 19, 2016. 

Contractor will be on-site to upgrade, clean and improve the efficiency of the existing HVAC ductwork.  Building electrical power will be ON during this HVAC and duct cleaning upgrade project by VENTTEC.  The fire alarm system will be properly coordinated with the appropriate UVM PPD maintenance zone during the project.

IMPORTANT PROJECT INFORMATION

Contractor will be on site from 7:00 am – 5:00 pm, during the weeks of August 1, August 8 & August 15 (08/19/2016 estimated completion date).  The Contractor will be identified clearly with their “VENTTEC” company logo / badge.  UVM personnel will also be on site to support the hired contractor – VENTTEC.  Please contact UVM Project Manager (noted below), if there are any problems and/or concerns.  There will be minor noise issues in the building ductwork area(s). Every effort will be made to minimize this noise during the UVM weekday business hours.

Physical Plant Contact

 Richard Wolbach, Project Manager

Richard.Wolbach@uvm.edu

802 656-8213.