TASK TABLE
|
DATE
|
|
Divide
into groups of 3-4 members. Submit (to Don Ross) group members names
and project choice and a short explanation on why your group is
interested in that choice.
|
No
later than September 7
|
|
Additional
project information supplied to each group (e.g. last year’s reports).
|
Week
of Sept. 10
|
|
Turn
in a rough draft description of project objectives and plans to
accomplish objectives (0.5-1 page) to Don Ross and consultant.
Arrange a meeting with your
consultant for Sept 21 or at their convenience.
|
September
14
|
|
Meet
with consultants and design sampling plan.
|
September 21
|
|
Turn
in sampling plan and a clear statement of project objectives to Don
Ross and consultant.
|
September 28
|
|
Sample!!!
Obtain bottles and sampling equipment from Agata or Don Ross. Follow
sampling protocols and QA/QC plan. Deliver samples for cation or anion
analysis to Don Ross. Determine SRP, pH, TSS, and/or extract soils with
assistance from Agata.
|
October
and November
|
|
Turn
in progress report to Don Ross and consultant detailing what has been
done and what remains to be done.
|
October
26
|
|
Absolute
deadline for sample submission to Don Ross.
|
November
9
|
|
Meet
with consultants to discuss findings.
|
November 16
|
|
Meet
with Don Ross for final review (optional).
|
Before Nov. 30
|
|
Oral
presentations of project.
|
November
30
|
Submit final report to
Don Ross
|
December 7
|