The details that follow are an initial series of questions, issues, and program reductions in response to the November 26, 2003 Technology Program and Cost Estimates from The Sextant Group. These details are a compilation from a meeting between Student Life, Media Services, and Computer and Information Technology (CIT), and are in no way inclusive and complete. More time is necessary for dialogue and collaborative design discussions with all parties in the context of budget reduction and program balance.

 

Initial reactions with respect to equipment was what appeared to be an over abundance of equipment in areas that were glass on several walls and open on the other side. We want to explore the relationship between architectural design and the specification of flat screens in program areas. The reductions that follow were made with some understanding of design and program, but this needs to be explored further.

 

Future development in the world of technology and audio-visual should drive decisions concerning final proposals and bids. Wireless projection, flexibility of equipment and access, the number of ethernet ports and wireless availability in public areas, public email stations on each floors, dedicated space within the building to support all technology needs, and the level and flexibility of video conferencing in meeting rooms. The draft program does not appear dedicate square footage for switching equipment for network and voice, provide wireless capabilities throughout the facility, in building cellular support, and public telephones.

 

Attached as addendums are the rough email responses from Jim Whitby (Media Services) and Dean Williams (CIT).

 

 

 

 

INITIAL REDUCTION POSSIBILITIES (merged from discussions)

 

Room                       Equipment Reduced            Estimated Savings

Dining              Flat Screen by 3                        13,500

Bistro               Flat Screen by 3                        13,500

                       Projection TV                           6,000

Distribution       Mega System Allowance      250,000

Ballroom           Flat Screen                               4,500

Perf Theater      Downgrade Projection TV           15,000

Black Box          Downgrade Projection TV           10,000

Game Room        Flat Screen by 3                        13,500

                       Projection TV                           6,000

Student Life Cof  Projection TV                           6,000

Career Conf       Projection TV                           6,000

 

Distribution       Reduce Video Conf to 1               18,400

Dining              Reduce Source Components         1,281

                       Eliminate Lectern                     5,255

Pub                  Eliminate Lectern                     4,250

Ballroom           Reduce Source Devices                       8,198

                       Eliminate Computers                  4,950

                       Eliminate Lectern                     8,500

Medium Mtg      Eliminate Computer                   2,475

Small Mtg          Eliminate Computers                  2,475

Black Box          Reduce Mixing Console               15,000

 

                               TOTAL                              $414,784

 

 

 

ADDENDUMS

 

 

Addendum A

University Commons Project

Proposed Adjustments to Technology Scope

Notes by J.Whitby 12/11/04

 

Page 8

Distributed video:

-Scale down large format display at key public location.

-Head end source location sounds good adjacent to Info Desk.

-Kiosks could be simpler? Limited to UVM website access via touch

screen like ÒSmart Overlay SystemÓ Ðno keyboard.

 

Dining:

-Delete presenters lectern.

-Delete source devices.

-Provide wall interface plates for control of projector functions, screen, and input

connections for computer, A/V sources, w/network accessibility adjacent.

-Include distributed audio system with mic inputs/program output, ADA audio provision.

 

Page 9

Dining (conÕt)

-Delete gooseneck microphoneÉÉÉ..presenters lecternÉÉ..

-Keep wireless microphone system.

 

Pub/Bistro:

-Delete presenters lectern.

- Provide wall interface plates for computer input and A/V source inputs.

- Delete small audio mixing console and array of microphones but provide input

to the basic room audio system so a console could be interfaced.

 

Ballroom:

-Depending on the room ceiling height, motorized projector lifts

may not be necessary.

-Delete presenters lectern in each ÒroomÓ.

 

Page 10

Ballroom

-Provide wall interface plates to accept A/V and computer sources. -- - Do not

provide source components.

-Wall inputs and controls in each room must be able to be configured to feed

source signals to one or both projectorsÉsame for speech and presentation

audio & ADA hearing impaired systems.

-Delete fixed computers & lecterns and permanent microphones butÉ

-Provide wireless microphone capability with combined or single

ÒroomÓ configuration.

-Provide centralized control system with wall panel control in each ÒroomÓ.

 

Pre-function Area:

-Video display and audio should be selectable from either of the

ballroom ÒroomsÓ.

 

Meeting Rooms:

-Medium and small meeting rooms need only basic presentation

capabilityÉ..

-Large & Extra Large meeting rooms look ok.

Page 11

Videoconference Systems:

-Provide only one portable system to start with.

-Review videoconference needs with Wes Graff. (Pat Brown)

 

Performing Arts Theater:

-Delete large scale audio mixing console & related components

- Outsource contract as services are needed for large venue events.

(unless facility will have a full time dedicated tech support person).

 

Page 12

Performing Arts Theater:

-Keep all three bullet items for audio.

 

Rehearsal Theater:

-Delete large scale audio mixing console and outsource as needed

unless facility will have full time dedicated tech support person

-Provide small mixer for program audio mixing with provision for

large console interface as needed.

 

Rec./Game Room:

-Delete all bullet items on page 12 & 13 except provide background

music/paging system.

 

Student Life & Career Service Conf. Rooms: ???

-Add small, movable videoconference system for interviews etc.

 

 

QUESTION?? On page 6 there is a description of an Enhanced network Outlet that includes a Coax, but on Page 50 the Enhanced Outlet description does not list a Coax???

 

Page 42

Ballroom: ???Add Enhanced Outlet???

XLarge Meeting Room: ???Add Enhanced Outlet???

 

 

Page 43

Large Meeting Room: ???Add Enhanced Outlet???

 

 

SUGGESTED COST REDUCTIONS REDUCTION

 

Page 53

Vid Proj. Reduce large display allowance to $25,000 $225,000

Vid Conf.. Reduce to one portable unit to $18,400 18,400

 

Page 54 Does Software Development include system programming?

Cost for Support?? Who will operate??

 

Page55          Delete Source Components                 1,281

 

Page 57

Racks, Misc. Delete custom lectern,

ADD custom wall plate for A/V Computer.          3,250

Control Sys. Adjust control system allowance to reflect

No lectern and simplified control system.         5,255

Page 58

Vid Mon. Delete Projector -6,419

Source DevicesÉÉ.Rack mount Source componentsRacks, Misc.

Delete Lectern 4,250

 

Page 60

Source Devices: Delete Source Devices                8,198

Computer: Delete Computers 4,950

 

Page 61

Custom Control: Wall mount in each ÒroomÓ

Racks, Misc.: Delete Custom Lecterns 8,500

 

Page 63

Vid. Displays: Delete Displays, BUT pre-wire for them -9,698

 

Page 70

Computer: Delete Multimedia Computer -2,475

Page 72

Computer: Delete Multimedia                                                  2,475

 

Page74

Vid. Displays: Delete Displays, BUT pre-wire for them 14,547

 

Page 75 Delete Mixing Console & specialty mics. 40,000

Scale down audio system

Page 78

Vid. Proj. Scale back on video projector -8,000

Delete Mixing Console,                                 25,000

Scale down audio system

 

Page 81 Delete Projector, Source Devices, Sound Sys, Racks 14,157

and Control System.

Page 83

Computer: Delete Multimedia Computer -2,475

 

Page 85

Computer: Delete Multimedia Computer -2,475

____________

 

TOTAL REDUCTIONS - $406,805

 

 

 

Addedum B Ð Dean WilliamÕs Email

 

Pat, in preparation for our meeting tomorrow, here are some thoughts on principles for making choices, some possible reductions in spending, some additions, and some questions. In the process, I put the budget document online -- feel free to download your own copy of it from:

 

http://www.uvm.edu/cit/projects/student-commons/1507-UVM%20Commons-Tech%20Program%20Draft-112603-SW-unlocked.pdf

 

 

PRINCIPLES

[] Let's not make this a one-way building (to borrow Steve Cavrak's term). I count 30+ displays (one costing $250,000) and countless speakers sending officially controlled messages to students -- that won't make the building feel like theirs. It should not feel like an airport terminal. They should pick the channel.

 

[] Let's put priority on items that will be more expensive to add later (generally, infrastructure).

 

[] There are many areas that need to have wireless coverage on Day One; that seems not to be in the budget.

 

[] Let's not put in technology we don't have personnel to run, manage, and maintain, and that we don't have ongoing funding to replace. We need to estimate those costs. For example, replacing projector bulbs looks like at least 13 * $400 = $5,200 annually.

 

[] Let's see what students need when they really start using the rooms.

 

E.g., Let's have one nicely equipped meeting room instead of many, but provision the other rooms to add what may be needed later.

 

[] Can we assume mobile students will rarely need wired Ethernet ports; that it's just a relic of the "oh-oh's" (2001 - 2009)? Can we make the essential wired ports (e.g., offices) GigE, and do wireless elsewhere?

 

[] Technology costs for retail, food service, and fraternity space, should not be counted in whatever number we're trying to live within; those costs should be paid from other budgets (as indicated on p. 15, last item). So should departmental conference rooms.

 

 

SAVINGS

Some obvious potential cost savings to discuss:

 

[] eliminate ISDN (!)

 

[] Reduce wired Ethernet ports in:

 

- X Lg meeting room (24)

- Ballroom (29)

- SGA clubs (60)

- building staff (not Student Life) (30)

- prefunction lounge (10)

 

Savings for 86 ports * 252 = $21,672

 

[] Eliminate or scale back the Large Image Display (p. 53)

 

Savings: $250,000

 

[] Reduce number of 42" displays

 

Savings: Up to 29 x $4,849 = $ 140,621

 

[] Dining area video

 

- Are dining areas, with their interesting and attractive non-rectangular designs, really conducive to projectors and displays? Sound may be a good idea, but we should think twice about the video (unless Sodexho is buying, operating, and maintaining it).

 

Savings: Looks like $137,000.

 

[] Eliminate 8 of the 10 dedicated "multimedia computers" @ $2,475 each.

 

Savings: At least $19,800

 

Meeting rooms:

 

- numbers of rooms on p.52 does not match drawings

 

-- Increased ability to connect participants' laptops or tablets to LCD projectors would be good. It doesn't work well for the only connection to the projector to be at the lectern -- e.g., the CIT conference room. Can we do this wirelessly?

 

- Equip 1-2 rooms of each size like a Level I classroom ($10,000 each), rather than doing all of them

 

- Extra large: $52,000, roughly Level III; drop PC and VHS

 

Savings: roughly $2,800

 

- Large: Plan shows $51,000 each, roughly Level III; UVM Level III usually $35,000; might do one as Level III and one as Level I for $10,000

 

Savings: $40,000 - $57,000

 

- Medium: Plan shows $25,800 for roughly a Level II room; do as Level I for $10,000

 

Savings: 2 rooms x $15,000 savings = $30,000

 

- Small: same as medium, or provide no AV, just networking

 

Savings: 3 rooms x $15,000 = $45,000 [drawings show 5 rooms]

 

Theatres

 

- Are the uses of the theaters clearly enough defined to equip both of them for use as:

 

- classrooms (screen, projector, doc cameras, etc.)

- movies

- musical theatre and drama (instrument microphones, sound reinforcement etc.)

 

- Who is going to be responsible for running, maintaining, replacing?

 

[] Video conferencing -- do we need two? Or any, right away?

 

Savings: $36,800 or $73,600

 

[] Student Life and Career Services conference rooms

 

- $29,600 is a typical Level III room, like Williams 402.

 

- Should be a departmental, not project expense

 

- Do like a Level I, about $10,000? (Save $39,000)

 

[] Will VHS be dead by 2007?

 

---------> Total savings (minimum) . . . . . . . .. .. . . $ 762,693

 

 

ADDITIONS

 

 

[] Throughout halls, lounges -- Ethernet and power for clusters of 1-2 computers

 

[] Wireless in common areas on Day One (budget is contrary to design principle on p. 4) (but see QUESTIONS below concerning UVM expenses)

 

[] CATV does not seem to be included with DVD/VHS/computer sources in some locations, e.g., not in theatre (except lounge)

 

 

QUESTIONS

 

[] The $2.1M budget does not include some key UVM expenses (p. 16):

 

- network equipment

- voice equipment

- cable TV electronics

- security

 

-- Whose budget does the above come from?

 

 

[] Computer Lounge, p. 22 -- what is concept here? Is UVM providing any computers?

 

[] Is UVM providing any computers for student use in this building, either sit-down or stand-up stations? I don't see them, but I think it's realistic, even in 2007, to expect students to want to quickly check email, grades, etc. Even 3-4 computers on each floor, in halls or wherever, would be helpful (like VT Law School, Billings, etc.).

 

[] Coax outlets -- will work for std and HDTV? Can students choose channels to watch?

 

[] Are the phones in another plan?

 

[] Why is there a mix of Category 5e and 6e Ethernet cable?

 

[] Are budget calculations right in terms of quantities?

 

[] How does piano get to ballroom? ... stage ... orchestra pit ... rehearsal theatre

 

 

Roger Lawson said:

I like your analysis principles, and agree in particular that while we should be sure to include technology that would be much more costly to install after the building is complete. A "protected" allowance should be set aside for adding optional equipment after the use of the building and needs of students are clearer.

 

Fortunately, we will have a good bit of time before we actually have to make the technology choices. We will have a more accurate picture of what the technologies prevail and what students will want when we actually have to decide.

 

See you tomorrow morning!

 

-Dean

 

 

Hi all -

 

I am sorry I was not as last week's meeting, but would be happy to attend future meetings if you would find it helpful in your efforts to find savings on Commons technology.  In the meantime, here is some inputs from Network Services.  

 

>From a very high level:  

 

1)  This estimate includes a few, but not all the costs that will be incurred by Network Services.  On page 16 this is specified.  In fact the only Network Services costs included in this estimate is "the structured cabling system" for data voice and video.  Therefore, any savings I could contribute to reduce this cost estimate would have to come from that cost item.  

 

2)  In the Design Principles on page 4 bullet 2, the use of the UVM Telecom Infrastructure Standard is specified as a core Design Principle.  In our meetings with the architects we requested adherence to the standard and we were happy they agreed. This standard reflects historical "real world" demand for access at UVM. Our experience has taught us that when we deviate from this standard unmet demand will be identified as construction continues .  Reinstatement of these facilities during construction results in "change" orders which cause project "actual" costs to exceed the budgeted cost.  

 

3)  Specifically regarding ISDN - the elimination of ISDN from your estimate will not significantly reduce Network Services costs.  Here is the reason why.  An outlet intended for ISDN is provisioned with CAT6 wire -- just like an outlet that would be used for data or voice service.  Therefore if you eliminate the ISDN, you are simply eliminating one CAT6 cable from the drop.  If you eliminate the application all together, then the drop could have one less cable per ISDN line canceled.  However, if you still want to application to run on some other type of connectivity - well then you need the CAT6 wire back again.  A standard Network Outlet has 3 CAT6 cables and is costed out at $252.  A Basic Network Outlet has one CAT6 cable and costs out at $106.  So if you removed 2 cables from an outlet you would save about $146.  

See additional embedded comments below.

 

Roger Lawson wrote:

 

Dean,

 

Thanks for all your work on this -- you have certainly given it a thorough read.

I like your analysis principles, and agree in particular that while we should be sure to include technology that would be much more costly to install after the building is complete. A "protected" allowance should be set aside for adding optional equipment after the use of the building and needs of students are clearer.

 

Fortunately, we will have a good bit of time before we actually have to make the technology choices. We will have a more accurate picture of what the technologies prevail and what students will want when we actually have to decide.

 

I, too, wonder about needs of ISDN, especially in a few years when the building is complete and the campus network has even more capacity, and maybe even QoS capabilities. What do others think?

 

>From a network services perspective, the only costs included in this document for ISDN is for the CAT6 termination.  That CAT6 will be required for any connectivity you choose, whether it turns out to be ISDN or something else.  The only way you can eliminate that cable is to eliminate the whole application that the ISDN would be used for.

 

Roger